Version 7 (modified by 16 years ago) ( diff ) | ,
---|
Open Issues
author: Heikki Doeleman
This page lists the things still needed to be done in the ESA ebRIM project and estimates how many days of work they are.
issue list
- XPATH support in queries
0 days (considered out of scope)
- Security 1: create web service in legacy
3 days
- Security 2: use web service in ebRIM app
2 days
- Uploader web service
3 days
- ReferenceDataLoader
1 days
- ISO transformation
1 days
- Mousse au chocolat (façades in Persistence Layer)
2 days
- Mapping query fields to Lucene fields
1 days
- Stored Queries
1 days
- CSW operations: logical services : Erik
3 days
- CSW operations: JiBX mapping for domain objects : Jose
3 days
- Unit tests for ISO transformation
1 days
- Fix build script
1 days
TOTAL remaining days in this estimate: 22
PI factor: 20%
TOTAL expected remaining days: 26
Note:
See TracWiki
for help on using the wiki.