Version 25 (modified by 16 years ago) ( diff ) | ,
---|
Open Issues
author: Heikki Doeleman
This page lists the things still needed to be done in the ESA ebRIM project and estimates how many days of work they are.
New issue list
(1) Heikki checks tonight at differences in schemas and impact if we change. (2) Erik check tomorrow the axis layer (3) Erik tests with TeamEngine tomorrow and Wednesday (4) Jose implements convertRegistryObjectToAbstractRecor (5) sorting results (6) Jose ElementName (7) Jose Check XPathPropertyresolver issue (8) Erik the save facade does not seem to update when the same ISO metadata is offered a second time. Instead, it creates new ebrim stuff in addition to the earlier (9)Erik the ebrim updater in the legacy does not support deleting (10)Heiki: ebrim data created form esa iso testdata must be validated (11) Jose namespace in getrecords (12) Erik test the GET interface (13) Heikki test the GET interface (14) All test and validate everything like crazy
Old issue list
- XPATH support in queries
100%
- Security 1: create web service in legacy : Erik, Jose, Heikki
3 days, status 0%
- Security 2: use web service in ebRIM app : Erik, Jose, Heikki
2 days, status 0%
- Uploader web service : Heikki
0.3 days, 95% - still to do: look up classification IDs
- ReferenceMetadataInsertionService : Erik
100%
- ISO transformation
100%
- Mousse au chocolat (façades in Persistence Layer)
100%
- Mapping query fields to Lucene fields : Jose
0.5, 90% -- still to do : some issues
- Stored Queries : Jose, Heikki
1 days, status 0%
- CSW operations: logical services : Heikki, Erik
1.5 days -- still to do: finish getRecords & getCapabilities, impl DescribeRecord
- CSW operations: JiBX mapping for domain objects : Jose
0.1 days, status 99%
- UI for GetCapabilities : Erik
100%
- Joins : Jose
2 days, status 40%
- Stored queries : Jose
1 day, 0%
- Documentation, testing and stuff : Erik
2 days, 0%
- Fixing Hibernate : Erik
1 days, 50%
considered out of scope :
- Unit tests for ISO transformation : Heikki
1 days, status 0%
- Fix build script : Jeroen
there should be a single build script that builds an installer for the integrated application (currently you need to build domain, persistence, services, client, and web separately, then copy the client jar into legacy, then build legacy)
1 days
TOTAL remaining days in this estimate: 16
PI factor: 20%
TOTAL expected remaining days: 19.2
without security : 13.2 days
Availability (max) until Friday May 8th :
Jose : 4.5 days Erik : 6 days Heikki : 4 days