wiki:esaEbRIMToDo

Version 18 (modified by heikki, 15 years ago) ( diff )

--

Open Issues

author: Heikki Doeleman

This page lists the things still needed to be done in the ESA ebRIM project and estimates how many days of work they are.


issue list

  1. XPATH support in queries

100%

  1. Security 1: create web service in legacy : Erik, Jose, Heikki

3 days, status 0%

  1. Security 2: use web service in ebRIM app : Erik, Jose, Heikki

2 days, status 0%

  1. Uploader web service : Heikki

0.3 days, 95% - still to do: look up classification IDs

  1. ReferenceMetadataInsertionService : Erik

0.1, 95% -- still to do: init at startup

  1. ISO transformation

100%

  1. Mousse au chocolat (façades in Persistence Layer)

100%

  1. Mapping query fields to Lucene fields : Jose

0.5, 90% -- still to do : some issues

  1. Stored Queries : Jose, Heikki

1 days, status 0%

  1. CSW operations: logical services : Heikki, Erik

1.5 days -- still to do: finish getRecords & getCapabilities, impl DescribeRecord

  1. CSW operations: JiBX mapping for domain objects : Jose

0.1 days, status 99%

  1. UI for GetCapabilities : Erik

0.5 days, status 100%

  1. Joins : Jose

2 days, status 40%

  1. Stored queries : Jose

1 day, 0%

  1. Documentation, testing and stuff

2 days, 0%


considered out of scope / unwilling project members :

  1. Unit tests for ISO transformation : Heikki

1 days, status 0%

  1. Fix build script : Jeroen

there should be a single build script that builds an installer for the integrated application (currently you need to build domain, persistence, services, client, and web separately, then copy the client jar into legacy, then build legacy)

1 days


TOTAL remaining days in this estimate: 14

PI factor: 20%

TOTAL expected remaining days: 16.8

without security : 10.8 days