wiki:esaEbRIMToDo

Version 10 (modified by heikki, 16 years ago) ( diff )

--

Open Issues

author: Heikki Doeleman

This page lists the things still needed to be done in the ESA ebRIM project and estimates how many days of work they are.


issue list

  1. XPATH support in queries

0 days (considered out of scope)

  1. Security 1: create web service in legacy

3 days

  1. Security 2: use web service in ebRIM app

2 days

  1. Uploader web service

3 days

  1. ReferenceDataLoader

1 days

  1. ISO transformation

1 days

  1. Mousse au chocolat (façades in Persistence Layer) : Jose

2 days

  1. Mapping query fields to Lucene fields : Jose

1 days

  1. Stored Queries : Jose

1 days

  1. CSW operations: logical services : Erik

3 days

  1. CSW operations: JiBX mapping for domain objects : Jose

3 days

  1. Unit tests for ISO transformation

1 days

  1. Fix build script : Jeroen

there should be a single build script that builds an installer for the integrated application (currently you need to build domain, persistence, services, client, and web separately, then copy the client jar into legacy, then build legacy)

1 days


TOTAL remaining days in this estimate: 22

PI factor: 20%

TOTAL expected remaining days: 26


Note: See TracWiki for help on using the wiki.