12 | | 1. blah |
13 | | 2. blah |
| 12 | 1. XPATH support in queries |
| 13 | 0 days (considered out of scope) |
| 14 | 2. Security 1: create web service in legacy |
| 15 | 3 days |
| 16 | 3. Security 2: use web service in ebRIM app |
| 17 | 2 days |
| 18 | 4. Uploader web service |
| 19 | 3 days |
| 20 | 5. !ReferenceDataLoader |
| 21 | 1 days |
| 22 | 6. ISO transformation |
| 23 | 1 days |
| 24 | 7. Mousse au chocolat (façades in Persistence Layer) |
| 25 | 2 days |
| 26 | 8. Mapping query fields to Lucene fields |
| 27 | 1 days |
| 28 | 9. Stored Queries |
| 29 | 1 days |
| 30 | 10. CSW operations: logical services |
| 31 | 3 days |
| 32 | 11. CSW operations: JiBX mapping for domain objects |
| 33 | 3 days |
| 34 | 12. Unit tests for ISO transformation |
| 35 | 1 days |
| 36 | |
| 37 | TOTAL remaining days in this estimate: 21 |
| 38 | PI factor: 20% |
| 39 | TOTAL expected remaining days: 25 |
| 40 | |
| 41 | |
| 42 | |