Changes between Version 16 and Version 17 of esaEbRIMToDo
- Timestamp:
- Apr 27, 2009, 1:27:38 AM (15 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
esaEbRIMToDo
v16 v17 32 32 11. CSW operations: JiBX mapping for domain objects : Jose 33 33 0.1 days, status 99% 34 35 34 14. UI for GetCapabilities : Erik 36 35 0.5 days, status 100% 37 36 15. Joins : Jose 38 37 2 days, status 40% 39 16. Store queries : Jose38 16. Stored queries : Jose 40 39 1 day, 0% 40 41 ---- 41 42 42 43 considered out of scope / unwilling project members : … … 52 53 ---- 53 54 54 TOTAL remaining days in this estimate: 2255 TOTAL remaining days in this estimate: 12 55 56 56 57 PI factor: 20% 57 58 58 TOTAL expected remaining days: 2659 TOTAL expected remaining days: 14.4 59 60 60 61 ----