| 94 | |
| 95 | |
| 96 | [[BR]] |
| 97 | === Weekly Report 4 (19th June, 2016) === |
| 98 | |
| 99 | |
| 100 | WHAT I GOT DONE THIS WEEK: |
| 101 | |
| 102 | I have finished working on the complete automatization of the pyramidal approach: thanks to my mentors's help, I have found a proper way to solve this issue and now it works fine. |
| 103 | |
| 104 | I have fixed the issue related to OSSIM compiling. |
| 105 | |
| 106 | I have continued working on the automatic mask creation for lay-over areas in SAR imagery. |
| 107 | |
| 108 | I have begun drafting the mid-term report. |
| 109 | |
| 110 | |
| 111 | [[BR]] |
| 112 | WHAT I PLAN ON DOING NEXT WEEK: |
| 113 | |
| 114 | To finalize and submit the mid-term report. |
| 115 | |
| 116 | To fix bugs and review code. |
| 117 | |
| 118 | |
| 119 | [[BR]] |
| 120 | SOMETHING ON WHICH I AM BLOCKED: |
| 121 | |
| 122 | At the moment I am not blocked on anything. |