Changes between Version 4 and Version 5 of 54ReleasePlan
- Timestamp:
- Jan 25, 2009, 8:30:01 PM (15 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
54ReleasePlan
v4 v5 20 20 '''Planned Dates''' 21 21 22 * number 1 22 We will plan for 2 betas and 1 release candidate (RC) over a 4 week period after the code freeze (1 beta/RC per week each Wednesday). This will lead us to a final release around mid-March: 23 23 24 '''Release Manager (see MS RFC 34)''' 24 * Feature freeze - Fri. February 13th, 2009 25 * 5.2.0-beta1 - Wed. February 18th, 2009 26 * 5.2.0-beta2 - Wed. February 25th, 2009 27 * 5.2.0-rc1 - Wed. March 4th, 2009 28 * 5.2.0 (final) - Wed. March 11th, 2009 29 30 '''Release Manager (see [http://mapserver.org/development/rfc/ms-rfc-30.html MS RFC 34])''' 25 31 TBD 26 32