{{{ #!rst Mapserver 4.6.0 was released on June 14, 2005. The release plan is still available below for reference. --- This 4.6 release plan was agreed between the developers. Information below may still change slightly as the release progresses. Planned Dates ------------- Based on our experience with the other 4.x releases, we will plan for 3 betas over a 6 weeks period after the code freeze. This would lead us to a final release in early June: * Feature freeze - April 20th, 2005 * 4.6.0-beta1 - April 25th (done on 2005-04-26) * 4.6.0-beta2 - May 9th (done on 2005-05-11) * 4.6.0-beta3 - May 23rd (done on 2005-05-27) * 4.6.0-rc1 - May 30th (done on 2005-06-09) * 4.6.0 (final) - June 6th (done on 2005-06-14) CVS Tags/Branches? ------------------ * The main trunk (HEAD) in CVS is currently the 4.5 development version that we plan to release as 4.6 * The stable CVS branch for this release will be called "branch-4-6" (not created yet). * Current proposed date for creating "branch-4-6" is the date of the 4.6.0 release (around June 6th) * If post-4.6 developments require earlier branching then please bring up your request for branching on the -dev list. * The betas will be tagged in CVS as "rel-4-6-0-beta1", "rel-4-6-0-beta2", ... and the releases as "rel-4-6-0", "rel-4-6-1", etc... Bugzilla Conventions -------------------- In order to facilitate querying the bugzilla database for bugs that still need to be addressed for this release, we try to stick to the following conventions: * Bugs to be addressed for this release must have their target milestone set to "4.6 release" * Bugs/Enhancements? that can't make it in this release but that we may want to address at a later time should be marked with the "FUTURE" target milestone with a comment explaining that the bug is postponed and if possible a quick analysis * The target milestone on a bug should be set by the developers (bug owners) and not by the users (reporters). Other good practices when dealing with bugs: * Please file bugs for any non-trivial bugfix or change to the software. This is so that we keep a trace for future reference of all bugfixes and changes that were made (why and how). * Please mark bugs ASSIGNED as soon as you start working on them * Please when marking a bug fixed include a comment describing the fix, the version of the software in which it was done, and any other relevant information. This will just make our lives easier in a few months/years when questions come up about this issue. * When committing to CVS, please include the bug number in your CVS change log comment. * Keep documentation in mind when fixing/changing things: if you cannot update the documentation yourself then please create a documentation bug describing the new feature/change and which document(s) should be updated. The following query returns all currently open bugs that are tagged with the "4.6 release" target milestone: http://mapserver.gis.umn.edu/bugs/buglist.cgi?target_milestone=4.6+release&bug_status=NEW&bug_status=ASSIGNED&bug_status=REOPENED Open Tasks ---------- * Documentation updates - Coordinate with all documentation contributors to bring all documents up to date for the release * Resp: Kari * Bug #: * Status: Completed Tasks --------------- Once completed, the tasks above should be moved down here. * MapServer performance issue - Z and M cause performance lost * Resp: Julien * Bug #: 1244 * Status: Completed * MapServer performance issue - Label outline performance issue * Resp: Steve / Julien * Bug #: 1243 * Status: Set to Future, See bug for details * Layer tolerance - Tolerance default value should be based on the layer type * Resp: Steve / Julien * Bug #: 1103 * Status: Completed * GEOS Integration * Resp: Steve * Bug #: 770 * Status: done * Support for GML Profiles * Resp: Steve * Bug #: 950 * Status: done }}}