= Open Issues = author: Heikki Doeleman This page lists the things still needed to be done in the ESA ebRIM project and estimates how many days of work they are. [[BR]] ---- === issue list === 1. XPATH support in queries : Nobody 0 days (considered out of scope) 2. Security 1: create web service in legacy : Erik, Jose, Heikki 3 days, status 0% 3. Security 2: use web service in ebRIM app : Erik, Jose, Heikki 2 days, status 0% 4. Uploader web service : Heikki 3 days, status 70% 5. !ReferenceDataLoader : Heikki 1 days, status 0% 6. ISO transformation : Heikki 1 days, status 0% 7. Mousse au chocolat (façades in Persistence Layer) : Jose 2 days, status 50% 8. Mapping query fields to Lucene fields : Jose 1 days, status 30% 9. Stored Queries : Jose 1 days, status 0% 10. CSW operations: logical services : Erik 3 days, status 20% 11. CSW operations: JiBX mapping for domain objects : Jose 3 days, , status 50% 12. Unit tests for ISO transformation : Heikki 1 days, status 0% 13. Fix build script : Jeroen there should be a single build script that builds an installer for the integrated application (currently you need to build domain, persistence, services, client, and web separately, then copy the client jar into legacy, then build legacy) 1 days ---- TOTAL remaining days in this estimate: 22 PI factor: 20% TOTAL expected remaining days: 26 ----