= Open Issues = author: Heikki Doeleman This page lists the things still needed to be done in the ESA ebRIM project and estimates how many days of work they are. [[BR]] ---- === issue list === 1. XPATH support in queries 0 days (considered out of scope) 2. Security 1: create web service in legacy 3 days 3. Security 2: use web service in ebRIM app 2 days 4. Uploader web service 3 days 5. !ReferenceDataLoader 1 days 6. ISO transformation 1 days 7. Mousse au chocolat (façades in Persistence Layer) 2 days 8. Mapping query fields to Lucene fields 1 days 9. Stored Queries 1 days 10. CSW operations: logical services : Erik 3 days 11. CSW operations: JiBX mapping for domain objects : Jose 3 days 12. Unit tests for ISO transformation 1 days 13. Fix build script 1 days ---- TOTAL remaining days in this estimate: 22 PI factor: 20% TOTAL expected remaining days: 26 ----