wiki:esaEbRIMToDo

Version 30 (modified by heikki, 15 years ago) ( diff )

--

Open Issues

author: Heikki Doeleman

This page lists the things still needed to be done in the ESA ebRIM project and estimates how many days of work they are.


New issue list

(1) Done: Heikki checks tonight at differences in schemas and impact if we change.

(2) Done: Erik check tomorrow the axis layer

(3) Erik tests with TeamEngine tomorrow and Wednesday

(4) Done: Jose implements convertRegistryObjectToAbstractRecor

(5) sorting results

(6) Jose ElementName

(7) Done: Jose Check XPathPropertyresolver issue

(8) Erik the save facade does not seem to update when the same ISO metadata is offered a second time. Instead, it creates new ebrim stuff in addition to the earlier

  • The save facade does not seem to update when the same ISO metadata is offered a
  • second time. Instead, it creates new ebrim stuff in addition to the earlier
  • Status: The problem cannot be reproduced in a unit test (RegistryObjectListStoreFacadeTest). What is the problem?

The problem was that when I inserted the same ISO more than once in the legacy, (with same UUID), the number of ebrim objects would increase after every insertion. It should remain the same if a real update was happening.

(9)Erik the ebrim updater in the legacy does not support deleting

(10)Heiki: ebrim data created form esa iso testdata must be validated

(11) Jose namespace in getrecords

(12) Erik test the GET interface

(13) Heikki test the GET interface

(14) All test and validate everything like crazy

(15) ReferenceMetadataInsertionServiceTest is failing because of problem in Jibx binding

Old issue list

  1. XPATH support in queries

100%

  1. Security 1: create web service in legacy : Erik, Jose, Heikki

3 days, status 0%

  1. Security 2: use web service in ebRIM app : Erik, Jose, Heikki

2 days, status 0%

  1. Uploader web service : Heikki

0.3 days, 95% - still to do: look up classification IDs

  1. ReferenceMetadataInsertionService : Erik

100%

  1. ISO transformation

100%

  1. Mousse au chocolat (façades in Persistence Layer)

100%

  1. Mapping query fields to Lucene fields : Jose

0.5, 90% -- still to do : some issues

  1. Stored Queries : Jose, Heikki

1 days, status 0%

  1. CSW operations: logical services : Heikki, Erik

1.5 days -- still to do: finish getRecords & getCapabilities, impl DescribeRecord

  1. CSW operations: JiBX mapping for domain objects : Jose

0.1 days, status 99%

  1. UI for GetCapabilities : Erik

100%

  1. Joins : Jose

2 days, status 40%

  1. Stored queries : Jose

1 day, 0%

  1. Documentation, testing and stuff : Erik

2 days, 0%

  1. Fixing Hibernate : Erik

1 days, 50%


considered out of scope :

  1. Unit tests for ISO transformation : Heikki

1 days, status 0%

  1. Fix build script : Jeroen

there should be a single build script that builds an installer for the integrated application (currently you need to build domain, persistence, services, client, and web separately, then copy the client jar into legacy, then build legacy)

1 days


TOTAL remaining days in this estimate: 16

PI factor: 20%

TOTAL expected remaining days: 19.2

without security : 13.2 days


Availability (max) until Friday May 8th :

Jose : 4.5 days Erik : 6 days Heikki : 4 days